Umlazi T Community Residential Unit (CRU) Project

GovNews archive

From the GovNews archive. Names, appointments and project details reflect the original publication and may have changed.

Listen to this article
Location: Umlazi T-Section, Ward 89, Durban, KwaZulu-Natal
Type: Community rental housing for low-income households (R800–R3,500/month)

Client: eThekwini Metropolitan Municipality
Funding: KwaZulu-Natal Department of Human Settlements
Contractors: Varies by phase; Phase 1 handled by Mandlethu Projects (2009 pilot)
Project Value: Approx. R31 million – R60 million per phase
Total CRU investment in Umlazi area: Over R111 million

Phases and Dates:

2009 – Pilot phase began under Mandlethu Projects

2022 to 2024 – Phase 2: Construction of 54 units began, extended to April 2025

June 2024 – Tender issued for Phase 3A: 96 new units

November 2024 – Oversight visit confirmed 2 of 9 blocks were under construction

Challenges:

Delays from structural issues in old hostels

Tensions over procurement; DA and IFP questioned R19.1 million extension

Residents in nearby units faced poor services, non-payment issues

CRU design criticized for not matching cultural/household needs